| Time Plan |
|
|
|
The following timetable describes the projected timetable for construction and furnishing. May-December 2008 Architectural Work January-March 2009 Tender Bids April 2009-January 2010 Construction January-February 2010 Completion of Site Works March 2010 Completion of Furnishings May 2010 Library Opens |